Life-Cycle Cost and Greenhouse Gas Trade-Offs of Phosphorus-Removal Upgrading Pathways for China’s Municipal Wastewater Treatment Plants
Xiaoqian Sun, Yibei Wang, Wenhe Wang, Xue Niu, Chengbin Xu, Fei Guo, Yuanrong ZhuChina’s municipal wastewater treatment plants (WWTPs) increasingly require phosphorus-removal upgrading to meet the Class IA standard, creating trade-offs among chemical use, energy demand, cost, and greenhouse gas (GHG) emissions. This study compared six upgrading pathways for a 10,000 m3/d anaerobic–anoxic–oxic (AAO) WWTP by integrating GPS-X simulation, a life cycle assessment, process-based GHG accounting, and life-cycle costing. All pathways achieved the Class IA total phosphorus target but differed in polyaluminum chloride (PAC) demand, electricity consumption, and sludge production. Process-based GHG emissions ranged from 0.424 to 0.580 kg CO2-eq/m3, while discounted life-cycle costs ranged from 0.324 to 0.375 RMB/m3. P4, combining AAO with sand filtration (SF) and PAC dosing at the secondary clarifier, achieved the lowest cost, whereas P6, combining AAO, high-efficiency sedimentation (HES), and SF, exhibited the lowest GHG intensity. Optimizing the PAC dosing location reduced the chemical demand and associated burdens without additional infrastructure. At the national scale, Scenario 1 achieved both a GHG reduction and net cost savings, whereas Scenario 3 delivered the largest GHG reduction at the highest additional net cost. Sensitivity and uncertainty analyses supported the main cost–carbon trade-off while revealing uncertainty in the economic ranking of closely performing pathways. These findings support integrated environmental and economic decision-making for phosphorus-removal upgrading.