From Static Risk Registers to Phase-Adaptive Risk Analytics: A Market-to-Credit Monitoring Framework for Renewable Energy Projects in Bulgaria

Ivelina Shtereva, Daniel Yordanov, Nikolay Sterev

Static risk registers compiled at financial close do not follow the market conditions that determine the cash flows of merchant-exposed renewable projects. This study asks how far public day-ahead market data can support a phase-adaptive decision-support and monitoring framework for market-to-credit risk in solar-dominated renewable projects in Bulgaria. It uses 1096 daily observations (13 July 2023–12 July 2026) of day-ahead prices, renewable generation, and interpolated installed capacity. Across thirteen price specifications, the capacity coefficient is a conditional association that cannot be separated from time trends and has the sign opposite to the merit-order hypothesis, and same-day generation shows no stable negative association with the daily average price. In 730 rolling-origin forecasts, the capacity-and-trend model improves on a naive forecast by 5.9%, but not on an AR(1) benchmark, whereas calendar terms reduce the root-mean-squared error by about 25%. Days with a negative minimum price rise from 15 to 44 per sample year. Candidate monitoring indicators do not outperform a seasonal benchmark in the test sample and are not validated early-warning signals. A rolling debt service coverage ratio (DSCR) analysis of a stylized 1 MW PV asset rests on assumed capture rates, generation profiles, and financing terms, not on observed project data; under the base structure, no 12-month window breaches a 1.20× reference value at a capture rate of 0.70, and breaches appear only at lower capture rates or under tighter structures. These scenario results do not generalize, and the framework requires project-level validation.

More from our Archive